Installation of Sockitz products are as easy as following these simple steps

All electrical installation work should be carried out by qualified
competent persons, to BS7671 IEE wiring regulations

Step One

First Fix - backbox and wiring installed as usual.

Step Two

Second Fix - Fit Safety Shield, along with socket a complete tests.

Step Three

Electrical supply is safely maintained during remaining building work, electrician can leave site.

Step Four

Plaster, patch, tile or paint. A shower cap or plastic back should be used to keep the accessory clean and free from dust while this work is completed.

Step Five

Remove fixing screws, snap and remove Safety Shield, replace fixing screws, carry out final checks & tests.

Step Six

Job Complete.